By Lisa Iesse Writer HAMILTON – Ontario’s ministry of environment has pulled the brakes on 8,000 cubic metres or 16,000 tons of Chedoke Creek waste enroute to a local suburban landfill site in Hamilton. About one month ago, in a message posted on their website the city announced the clean-up was complete. “The in-water targeted dredging activities are completed, concluding the four-month effort to remove sediment from the bottom of Chedoke Creek.” It was a job that came with a $10.4 million price tag. “We’re running around 32 trucks a day of dried material as we’re able to,” Nick Winters, the city’s director of water told city council on November 21. About 2 weeks ago, the province stepped in warning that the planned dumping site, the GFL landfill in Stoney